This page contains information from our monthly construction reports, and provides detail about where our campus community may find mobility obstructed by construction activities.
We gather details on projects from our teams and the City of Denton but, at times, there may be projects that impede vehicle/pedestrian traffic. To report a project that will impede vehicle and/or pedestrian traffic for more than seven days, complete this form.
Project Name: Mulberry Street Utilities
Areas Impacted: Mulberry Street between Ave C and D closed to all automobile and pedestrian
traffic. Parking on Avenue D may be disrupted throughout the project.
Project Manager: City of Denton
Project Start Date: 2026-04-13
Project End Date: 2026-05-26
Location Description: Mulberry Street between Avenue C and Avenue D, and Avenue D
between Hickory and Sycamore
Project Summary: Upgrading water utilities
Project Name: Bonnie Brae Street Widening
Areas Impacted: Vehicular traffic to Mean Green Village will be intermittently disrupted.
Traffic to DATCU Stadium and Victory Hall may be disrupted. No pedestrian access.
Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary: Installation of underground utilities and roadway expansion to four-lane
divided highway.
Project Name: Bernard Street Roadwork
Areas Impacted: Automobile traffic will be disrupted throughout the project. Crosswalks
may not be accessible.
Project Manager: City of Denton
Project Start Date: 2026-02-04
Project End Date: 2026-07-01
Location Description: Bernard Street between Hickory and Chestnut
Project Summary: Utilities replacement and road reconstruction
Project Name: Science and Tech. Building
Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of
the project.
Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary: Construction of new Science and Tech. building.
Areas Impacted: Parking in Lot 40 and Greek Life Center may be intermittently disrupted. Lot 40 access from Highland Street only. Sidewalk access along Maple Street.
Project Manager: UNT Facilities
Project Start Date: 2026-03-25
Project End Date: 2026-08-01
Location Description: Lot 40
Project Summary: Renovation of parking lot
Areas Impacted: Vehicular traffic to Mean Green Village will be intermittently disrupted. Traffic to DATCU Stadium and Victory Hall may be disrupted. No pedestrian access.
Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary: Installation of underground utilities and roadway expansion to four-lane divided highway.
Project Name: North Bonnie Brae Street Widening
Areas Impacted: Travel between Main Campus and Discovery Park will be disrupted throughout
project duration and may need to be rerouted.
Project Manager: City of Denton
Project Start Date: 2026-02-02
Project End Date: 2026-03-13
Location Description: Bonnie Brae between Riney Road and US-77/Elm Street
Project Summary: Installation of underground utilities and roadway expansion to four-lane
divided highway.
Project Name: Bernard Street Roadwork
Areas Impacted: Automobile traffic will be disrupted throughout the project. Crosswalks
may not be accessible.
Project Manager: City of Denton
Project Start Date: 2026-02-04
Project End Date: 2026-07-01
Location Description: Bernard Street between Hickory and Chestnut
Project Summary: Utilities replacement and road reconstruction
Project Name: Science and Tech. Building
Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of
the project.
Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary: Construction of new Science and Tech. building.
Project Name: Clark Park Electrical Lines
Areas Impacted: Sidewalk and pedestrian access to Clark Park may be intermittently
disrupted.
Project Manager: Carl Parsons
Project Start Date: 2026-01-16
Project End Date: 2026-03-06
Location Description: Maple Street and Clark Park
Project Summary: Upgrades to electrical distribution and replacement of overhead
lines
Project Name: Bruce Hall Courtyard
Areas Impacted: Pedestrian traffic will be diverted around the area for the duration
of the project.
Project Manager: UNT Facilities
Project Start Date: 2026-01-19
Project End Date: 2026-03-27
Location Description: Courtyard and sidewalk between Bruce Hall and Life Sciences
Complex
Project Summary: Upgrades to drainage and sidewalk replacement
Project Name: Life Science Bioswale
Areas Impacted: Pedestrian access to the area may be intermittently disrupted.
Project Manager: Brandon Lacy
Project Start Date: 2026-03-02
Project End Date: 2026-08-31
Location Description: Retention Bioswale at Life Science Complex
Project Summary: Renovation of drainage and landscaping
Project Name: Highland Garage Landscaping
Areas Impacted: Vehicular and pedestrian traffic may be intermittently disrupted.
Project Manager: Brandon Lacy
Project Start Date: 2026-03-02
Project End Date: 2026-04-24
Location Description: Highland Street between Avenue A and Central
Project Summary: Renovation of landscaping
Project Name: Bruce Hall Courtyard
Areas Impacted: Pedestrian traffic will be diverted around the area for the duration
of the project.
Project Manager: UNT Facilities
Project Start Date: 2026-01-19
Project End Date: 2026-02-13
Location Description: Courtyard and sidewalk between Bruce Hall and Life Sciences
Complex
Project Summary: Upgrades to drainage and sidewalk replacement
Project Name: Clark Park Electrical
Areas Impacted: Sidewalk and pedestrian access to Clark Park may be intermittently
disrupted.
Project Manager: Carl Parsons
Project Start Date: 2026-01-16
Project End Date: 2026-02-27
Location Description: Maple Street and Clark Park
Project Summary: Upgrades to electrical distribution and replacement of overhead
lines
Project Name: Science and Tech. Building
Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of
the project.
Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary: Construction of new Science and Tech. building.
Project Name: Bonnie Brae Street Widening
Areas Impacted: Vehicular traffic to Mean Green Village will be intermittently disrupted.
Traffic to DATCU Stadium and Victory Hall may be disrupted. No pedestrian access.
Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary: Installation of underground utilities and roadway expansion to four-lane
divided highway.
Project Name: Prairie Street Roadwork
Areas Impacted: Automobile traffic impacted on Prairie St between Bernard and Welch.
Crosswalks may not be accessible.
Project Manager: City of Denton
Project Start Date: 2025-11-05
Project End Date: 2026-03-05
Location Description: Prairie Street between Bernard and Welch
Project Summary: Utilities replacement and road reconstruction
Project Name: Bernard Street Roadwork
Areas Impacted: Automobile traffic will be disrupted throughout the project. Crosswalks
may not be accessible.
Project Manager: City of Denton
Project Start Date: 2026-01-30
Project End Date: 2026-07-24
Location Description: Bernard Street between Hickory and Chestnut
Project Summary: Utilities replacement and road reconstruction
Project Name: Sycamore and Welch Construction
Areas Impacted: Intersection will not be accessible to vehicular traffic during construction.
Pedestrian crosswalks may not be available.
Project Manager: City of Denton
Project Start Date: 2025-12-15
Project End Date: 2026-01-10
Location Description: Intersection of Sycamore and Welch
Project Summary: Installation of Traffic Control signals. Will be completed prior
to Spring semester 2026.
Project Name: Pollinative Prairie Walkway
Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily
disrupted during construction.
Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2026-01-09
Location Description: Discovery Park Pollinative Prairie
Project Summary: Addition of covered pavilion and seating for Pollinative Prairie
at Discovery Park campus. Will be completed prior to Spring semester 2026.
Project Name: Prairie Street Construction
Areas Impacted: Automobile traffic impacted on Prairie St between Bernard and Welch.
Crosswalks may not be accessible.
Project Manager: City of Denton
Project Start Date: 2025-11-05
Project End Date: 2026-03-31
Location Description: Prairie Street between Bernard and Welch
Project Summary: Utilities replacement and road reconstruction.
Project Name: Bonnie Brae St Widening
Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted
for the duration of the project.
Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street between Airport Rd and Roselawn Dr
Project Summary: Installation of underground utilities and roadway expansion to four-lane
divided highway.
Project Name: Science and Tech. Building
Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of
the project.
Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary: Construction of new Science and Tech. building.
Project Name: Chilton Parking Upgrades
Areas Impacted: Sidewalk north of Chilton along Chestnut Street will be blocked for one week. Automobile traffic will be minimally impacted.
Project Manager: Neely Shirey
Project Start Date: 2025-01-05
Project End Date: 2026-01-10
Location Description: Chestnut Street entrance to Chilton Hall
Project Summary: Installation of ADA Van accessible parking space.
Project Name: Bonnie Brae St Widening
Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted
for the duration of the project.
Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary: Installation of underground utilities and roadway expansion to four-lane
divided highway.
Project Name: Welch St Construction
Areas Impacted: No automobile traffic on Welch St between Prairie and Highland. No
crosswalk available. Pedestrian crosswalk at Central and Highland.
Project Manager: City of Denton
Project Start Date: 2025-09-15
Project End Date: 2025-11-26
Location Description: Welch Street between Prairie and Highland
Project Summary: Utilities replacement and road reconstruction
Project Name: Welch St Construction
Areas Impacted: No automobile traffic on Welch St between Hickory and Mulberry. No
accessible crosswalk at Mulberry and Welch.
Project Manager: City of Denton
Project Start Date: 2025-10-01
Project End Date: 2025-12-05
Location Description: Welch Street between Hickory and Mulberry
Project Summary: Utilities replacement and road reconstruction
Project Name: Prairie St Construction
Areas Impacted: No automobile traffic on Prairie St between Bernard and Welch. Crosswalks
may not be accessible.
Project Manager: City of Denton
Project Start Date: 2025-11-05
Project End Date: 2026-03-31
Location Description: Prairie Street between Bernard and Welch
Project Summary: Utilities replacement and road reconstruction
Project Name: Sycamore and Welch Construction
Areas Impacted: Intersection will not be accessible to vehicular traffic during construction.
Pedestrian crosswalks may not be available.
Project Manager: City of Denton
Project Start Date: 2025-12-15
Project End Date: 2026-01-10
Location Description: Intersection of Sycamore with Welch
Project Summary: Installation of Traffic Control signals
Project Name: Union Circle and Welch Construction
Areas Impacted: Intersection will not be accessible to vehicular traffic during construction.
Pedestrian crosswalks may not be available.
Project Manager: City of Denton
Project Start Date: 2025-12-20
Project End Date: 2026-01-03
Location Description: Intersection of Chestnut/Union Circle with Welch
Project Summary: Installation of Traffic Control signals
Project Name: Avenue C Lighting Installation
Areas Impacted: Vehicle traffic southbound on Avenue C will be redirected between
Chestnut and Maple. Northbound traffic may be temporarily disrupted. Sidewalks are
not affected.
Project Manager: Carl Parsons
Project Start Date: 2025-11-24
Project End Date: 2025-11-26
Location Description: Avenue C Southbound Lane
Project Summary: Installation of new street lighting masts
Project Name: Performing Arts Electrical
Areas Impacted: Minimal automobile and pedestrian impact. Trenches will be dug around
the north side of the buildings. Sidewalk access may be impacted intermittently.
Project Manager: Carl Parsons
Project Start Date: 2025-10-01
Project End Date: 2025-11-30
Location Description: Performing Arts Center and Annex
Project Summary: Upgrading electrical infrastructure to Performing Arts Center
Project Name: Bruce Hall Lighting Installation
Areas Impacted: Walkway between Bruce and Life Science will be intermittently disrupted.
Project Manager: Carl Parsons
Project Start Date: 2025-10-29
Project End Date: 2025-11-26
Location Description: Walkway between Bruce and Life Science
Project Summary: Installation of electrical infrastructure and lighting masts
Project Name: Highland Street Closure
Areas Impacted: Vehicle traffic must be pre-approved. Pedestrian access is not impacted.
Project Manager: UNT Facilities
Project Start Date: 2025-08-18
Project End Date: 2026-01-01
Location Description: Highland Street between Ave C and Ave A
Project Summary: Highland Street is pedestrian-only through the center of campus.
Non-approved traffic will be redirected.
Project Name: Science and Tech. Building
Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of
the project.
Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary: Construction of new Science and Tech building.
Project Name: Hickory Street Landscaping
Areas Impacted: Sidewalks along Hickory and leading into Hickory, Auditorium, and
Language buildings may be intermittently disrupted.
Project Manager: Brandon Lacy
Project Start Date: 2025-08-01
Project End Date: 2026-01-01
Location Description: Hickory, Auditorium, and Language building north lawns
Project Summary: Raising sidewalks and renovation of irrigation and landscaping.
Project Name: Softball Clubhouse Construction
Areas Impacted: Use of softball fields and batting facilities will be disrupted during
construction.
Project Manager: UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary: Improvement of dugouts and construction of new club house and offices.
Project Name: Sullivant Public Safety Center Parking Canopy
Areas Impacted: Minimal pedestrian impact, police parking will be disrupted.
Project Manager: Herman McKeiver
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: Sullivant Public Safety Center
Project Summary: Installation of parking canopy along west side of Sullivant.
Project Name: Pollinative Prairie Walkway
Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily
disrupted during construction.
Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2025-11-21
Location Description: Discovery Park Pollinative Prairie
Project Summary: Addition of covered sidewalk and benches at Pollinative Prairie
at Discovery Park campus.
Highland and Welch Construction
Areas Impacted: The intersection of Highland and Welch will be closed for 24 hours.
Local and bus traffic will be redirected. Sidewalks may be disrupted.
Project Manager: City of Denton
Start Date: November 24, 2025
End Date: November 26, 2025
Location Description: Intersection of Highland and Welch
Project Summary: Installation of utilities and road reconstruction
Project Name: Bonnie Brae St Widening
Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted
for the duration of the project.
Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary: Installation of underground utilities and roadway expansion to four-lane
divided highway.
Project Name: Welch St Construction
Areas Impacted: No automobile traffic on Welch St between Prairie and Highland. No
crosswalk available. Pedestrian crosswalk at Central and Highland.
Project Manager: City of Denton
Project Start Date: 2025-09-15
Project End Date: 2025-11-24
Location Description: Welch Street between Prairie and Highland
Project Summary: Utilities replacement and road reconstruction
Project Name: Welch St Construction
Areas Impacted: No automobile traffic on Welch St between Hickory and Mulberry. No
accessible crosswalk at Mulberry and Welch.
Project Manager: City of Denton
Project Start Date: 2025-10-01
Project End Date: 2026-01-02
Location Description: Welch Street between Hickory and Mulberry
Project Summary: Utilities replacement and road reconstruction
Project Name: Highland Street Closure
Areas Impacted: Vehicle traffic must be pre-approved. Pedestrian access is not impacted.
Project Manager: UNT Facilities
Project Start Date: 2025-08-18
Project End Date: 2026-01-01
Location Description: Highland Street between Ave C and Ave A
Project Summary: Highland Street is pedestrian-only through the center of campus.
Non-approved traffic will be redirected.
Project Name: Science and Tech. Building
Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of
the project.
Project Manager: Jay Henson, UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary: Construction of new Science and Tech. building.
Project Name: Hickory Street Landscaping
Areas Impacted: Sidewalks along Hickory and leading into Hickory, Auditorium, and
Language buildings may be intermittently disrupted.
Project Manager: Brandon Lacy
Project Start Date: 2025-08-01
Project End Date: 2026-01-01
Location Description: Hickory, Auditorium, and Language building north lawns
Project Summary: Raising sidewalks and renovation of irrigation and landscaping.
Project Name: Performing Arts Electrical
Areas Impacted: Minimal automobile and pedestrian impact. Trenches will be dug around
the north side of the buildings. Sidewalk access may be impacted intermittently.
Project Manager: Carl Parsons
Project Start Date: 2025-10-01
Project End Date: 2025-11-30
Location Description: Performing Arts Center and Annex
Project Summary: Upgrading electrical infrastructure to Performing Arts Center
Project Name: Intramural Fields Lighting and Irrigation Installation
Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage
road and Prairie Street
Project Manager: Herman McKeiver
Project Start Date: 2024-08-01
Project End Date: 2025-11-02
Location Description: Intramural Fields at Bonnie Brae and Prairie
Project Summary: Construction of new field lighting and irrigation systems for intramural
fields
Project Name: Softball Clubhouse Construction
Areas Impacted: Use of softball fields and batting facilities will be disrupted during
construction.
Project Manager: Jay Henson, UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary: Improvement of dugouts and construction of new club house and offices.
Project Name: Pollinative Prairie Walkway
Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily
disrupted during construction.
Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2025-11-21
Location Description: Discovery Park Pollinative Prairie
Project Summary: Addition of covered sidewalk and benches at Pollinative Prairie at
Discovery Park campus.
Project Name: Sullivant Public Safety Center Parking Canopy
Areas Impacted: Minimal pedestrian impact, police parking will be disrupted.
Project Manager: Herman McKeiver
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: Sullivant Public Safety Center
Project Summary: Installation of parking canopy along west side of Sullivant.
Project Name: Bonnie Brae Street Widening
Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.
Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary: Installation of underground utilities and roadway expansion to four-lane
divided highway.
Project Name: Science and Tech. Building
Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.
Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary: Construction of new Science and Tech. building.
Project Name: Union Circle Realignment
Areas Impacted: Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.
Project Manager: City of Denton
Project Start Date: 2025-05-14
Project End Date: 2025-10-01
Location Description: Union Circle
Project Summary: Street reconstruction and realignment. Traffic flow on Union Circle
will be reversed.
Project Name: Welch Street Construction
Areas Impacted: No automobile traffic on Welch St between Hickory and Mulberry. No accessible crosswalk at Mulberry and Welch.
Project Manager: City of Denton
Project Start Date: 2025-10-06
Project End Date: 2025-12-24
Location Description: Welch Street between Hickory and Mulberry
Project Summary: Utilities replacement and road reconstruction
Project Name: Welch Street Construction
Areas Impacted: No automobile traffic on Welch St between Prairie and Highland. No crosswalk available. Pedestrian crosswalk at Central and Highland.
Project Manager: City of Denton
Project Start Date: 2025-09-15
Project End Date: 2025-11-24
Location Description: Welch Street between Prairie and Highland
Project Summary: Utilities replacement and road reconstruction
Project Name: Welch and Prairie Traffic Signals
Areas Impacted: Intersection of Welch with Prairie and Union Circle will be closed to vehicular and pedestrian traffic. No accessible crosswalk available during construction.
Project Manager: City of Denton
Project Start Date: 2025-09-19
Project End Date: 2025-09-22
Location Description: Intersection of Welch and Prairie Streets
Project Summary: Installation of new traffic signals
Project Name: Fry and Hickory Lighting
Areas Impacted: Pedestrian crosswalks may be disrupted during construction. Accessible pathways may not be available.
Project Manager: City of Denton
Project Start Date: 2025-09-01
Project End Date: 2025-12-22
Location Description: Intersection of Hickory Street with Fry Street and Avenue A
Project Summary: Upgrading intersection lighting and crosswalks
Project Name: Softball Clubhouse Construction
Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.
Project Manager: UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary: Improvement of dugouts and construction of new club house and offices.
Project Name: Intramural Fields Lighting and Irrigation Installation
Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street
Project Manager: Herman McKeiver
Project Start Date: 2024-08-01
Project End Date: 2025-10-02
Location Description: Intramural Fields at Bonnie Brae and Prairie
Project Summary: Construction of new field lighting and irrigation systems for intramural
fields
Project Name: GAB Sidewalk Improvements
Areas Impacted: Pedestrian access to GAB from the west will be disrupted throughout the project.
Project Manager: Randy Salsman
Project Start Date: 2025-09-22
Project End Date: 2025-10-24
Location Description: Courtyard West of General Academic Building
Project Summary: Replace and raise concrete sidewalks.
Project Name: Sullivant Public Safety Center Parking Canopy
Areas Impacted: Minimal pedestrian impact, police parking will be disrupted.
Project Manager: Herman McKeiver
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: Sullivant Public Safety Center
Project Summary: Installation of parking canopy along west side of Sullivant.
Project Name: Pollinative Prairie Walkway
Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily disrupted during construction.
Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2025-11-21
Location Description: Discovery Park Pollinative Prairie
Project Summary: Addition of covered sidewalk and benches at Pollinative Prairie
at Discovery Park campus.
Project Name: Highland Street Closure
Areas Impacted: Vehicle traffic must be pre-approved. Pedestrian access is not impacted.
Project Manager: UNT Facilities
Project Start Date: 2025-08-18
Project End Date: 2026-01-01
Location Description: Highland Street between Ave C and Ave A
Project Summary: Highland Street is pedestrian-only through the center of campus.
Non-approved traffic will be redirected.
Project Name: Hickory Street Landscaping
Areas Impacted: Sidewalks along Hickory and leading into Hickory, Auditorium, and Language buildings may be intermittently disrupted.
Project Manager: Brandon Lacy
Project Start Date: 2025-08-01
Project End Date: 2025-11-28
Location Description: Hickory, Auditorium, and Language building north lawns
Project Summary: Renovation of irrigation and landscaping
Project Name: Performing Arts Electrical
Areas Impacted: Minimal automobile and pedestrian impact. Trenches will be dug around the north side of the buildings. Sidewalk access may be impacted intermittently.
Project Manager: Carl Parsons
Project Start Date: 2025-10-01
Project End Date: 2025-11-15
Location Description: Performing Arts Center and Annex
Project Summary: Upgrading electrical infrastructure to Performing Arts Center
Project Name: Music Building Plumbing Upgrade
Areas Impacted: Pedestrian crosswalk not available. Building entrances are not affected.
Project Manager: UNT Facilities
Project Start Date: 2025-09-19
Project End Date: 2025-10-10
Location Description: South courtyard crosswalk at Music Building
Project Summary: Upgrading hot water infrastructure for Music Building
Project Name: Performing Arts Electrical
Areas Impacted: Minimal automobile and pedestrian impact. Trenches will be dug around
the north side of the buildings. Sidewalk access may be impacted intermittently.
Project Manager: Carl Parsons
Project Start Date: 2025-01-01
Project End Date: 2025-11-15
Location Description: Performing Arts Center and Annex
Project Summary: Upgrading electrical infrastructure to Performing Arts Center
Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted
for the duration of the project.
Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Road to Roselawn Drive
Project Summary: Installation of underground utilities and roadway expansion to four-lane
divided highway.
Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.
Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street
Project Summary: Construction of new Science and Tech. building.
Project Name: Union Circle Realignment
Areas Impacted: Union Circle. Impacts access to the University Union, Matthews Hall
Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot
37.
Project Manager: City of Denton
Project Start Date: 2025-05-14
Project End Date: 2025-10-01
Location Description: Union Circle
Project Summary: Street reconstruction and realignment. Traffic flow on Union Circle
will be reversed.
Project Name: Welch Street Construction
Areas Impacted: No automobile traffic on Welch St between Mulberry and Sycamore. No
accessible crosswalk at Mulberry and Welch. Pedestrian crosswalk at Sycamore.
Project Manager: City of Denton
Project Start Date: 2025-07-07
Project End Date: 2025-10-01
Location Description: Welch Street between Mulberry and Sycamore
Project Summary: Utilities replacement and road reconstruction.
Project Name: Welch Street Construction
Areas Impacted: No automobile traffic on Welch St between Prairie and Highland. Pedestrian
crosswalk at Highland.
Project Manager: City of Denton
Project Start Date: 2025-09-03
Project End Date: 2025-11-24
Location Description: Welch Street between Prairie and Highland
Project Summary: Utilities replacement and road reconstruction.
Project Name: Welch and Chestnut Traffic Signals
Areas Impacted: Intersection of Welch with Chestnut and Union Circle will be closed
to vehicular and pedestrian traffic. No accessible crosswalk available during construction.
Project Manager: City of Denton
Project Start Date: 2025-09-17
Project End Date: 2025-09-19
Location Description: Intersection of Welch and Chestnut Streets
Project Summary: Installation of new traffic signals and crosswalks.
Project Name: Welch and Prairie Traffic Signals
Areas Impacted: Intersection of Welch with Prairie and Union Circle will be closed
to vehicular and pedestrian traffic. No accessible crosswalk available during construction.
Project Manager: City of Denton
Project Start Date: 2025-09-19
Project End Date: 2025-09-22
Location Description: Intersection of Welch and Prairie Streets
Project Summary: Installation of new traffic signals and crosswalks.
Project Name: Softball Clubhouse Construction
Areas Impacted: Use of softball fields and batting facilities will be disrupted during
construction.
Project Manager: UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary: Improvement of dugouts and construction of new club house and offices.
Project Name: Intramual Fields Lighting and Irrigation Installation
Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage
road and Prairie Street.
Project Manager: Herman McKeiver
Project Start Date: 2024-08-01
Project End Date: 2025-09-01
Location Description: Intramural Fields at Bonnie Brae and Prairie
Project Summary: Construction of new field lighting and irrigation systems for intramural
fields.
Project Name: Discovery Park Fire Piping Replacement
Areas Impacted: Parking lots and sidewalks leading to Discovery Park will be impacted.
Trenches dug in phases around the building exterior.
Project Manager: Carl Parsons
Project Start Date: 2025-02-03
Project End Date: 2026-08-04
Location Description: Discovery Park
Project Summary: Fire piping to be replaced around building exterior, interior, and
installation of water pumps for expanded sprinkler system.
Project Name: Pollinative Prairie Walkway
Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily
disrupted during construction.
Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2025-11-21
Location Description: Discovery Park Pollinative Prairie
Project Summary: Addition of covered sidewalk and benches at Pollinative Prairie
at Discovery Park campus.
Project Name: Hickory Street Landscaping
Areas Impacted: Sidewalks along Hickory and leading into Hickory, Auditorium, and
Language buildings may be intermittently disrupted.
Project Manager: Brandon Lacy
Project Start Date: 2025-08-01
Project End Date: 2025-11-28
Location Description: Hickory, Auditorium, and Language building north lawns
Project Summary: Renovation of irrigation and landscaping.
Project Name: Sullivant Public Safety Center Parking Canopy
Areas Impacted: Minimal pedestrian impact, police parking will be disrupted.
Project Manager: Herman McKeiver
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: Sullivant Public Safety Center
Project Summary: Installation of parking canopy along west side of Sullivant.