View our interactive map of construction projects and roadwork

This page contains information from our monthly construction reports, and provides detail about where our campus community may find mobility obstructed by construction activities.

We gather details on projects from our teams and the City of Denton but, at times, there may be projects that impede vehicle/pedestrian traffic. To report a project that will impede vehicle and/or pedestrian traffic for more than seven days, complete this form.

July 2025 Report
Bonnie Brae St Widening

Project Manager: City of Denton
Start Date: 2024-01-01
End Date: 2026-12-31
Location: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Summary: Installation of underground utilities and roadway expansion to four-lane divided highway.
Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

 

Science and Tech. Building

Project Manager: Jay Henson, UNT System
Start Date: 2024-01-17
End Date: 2026-09-01
Location: Lot 7, between W Mulberry Street and W Sycamore Street.
Summary: Construction of new Science and Tech building.
Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

 

Intramural Fields Lighting and Irrigation Installation

Project Manager: Herman McKeiver, Yaggi Engineering
Start Date: 2024-08-01
End Date: 2025-09-01
Location: Intramural Fields at Bonnie Brae and Prairie
Summary: Construction of new field lighting and irrigation systems for intramural fields
Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.

 

Discovery Park Fire Piping Replacement

Project Manager: Carl Parsons, UNT
Start Date: 2025-02-03
End Date: 2026-08-04
Location: Discovery Park
Summary: Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system
Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.

 

Softball Clubhouse Construction

Project Manager: Jay Henson, UNT System
Start Date: 2025-02-03
End Date: 2025-12-31
Location: Mean Green Village Softball Field
Summary: Improvement of dugouts and construction of new club house and offices.
Use of softball fields and batting facilities will be disrupted during construction.

 

Mulberry St Construction

Project Manager: City of Denton
Start Date: 2024-12-03
End Date: 2025-07-30
Location: Mulberry Street
Summary: Upgrading city water and sewer lines and street reconstruction.
Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.

 

Welch St Construction

Project Manager: City of Denton
Start Date: 2025-03-13
End Date: 2025-07-15
Location: Welch St between Highland St and Eagle Dr
Summary: Road reconstruction
No automobile traffic on Welch St between Eagle and Highland. Westbound traffic may cross at Maple St. No sidewalk accessible across Maple St or Highland St.

 

Gateway Class Ring Sculpture

Project Manager: Brandon Lacy
Start Date: 2025-05-05
End Date: 2025-05-30
Location: Gateway Center
Summary: Installation of UNT Class Ring sculpture and base with lighting and drainage
Sidewalk beneath the arch of Gateway Center will be partially blocked, building entrances will remain accessible.

 

Chilton Hall Sidewalk Expansion

Project Manager: Brandon Lacy
Start Date: 2025-05-12
End Date: 2025-07-31
Location: Chilton Hall East Side
Summary: Landscaping upgrades and widening of sidewalk in front of Chilton Hall along Avenue C.
No sidewalk access along Avenue C. East entrance to Chilton Hall 2nd Floor will not be accessible.

 

Ave D and Chestnut Street Construction

Project Manager: City of Denton
Start Date: 2025-05-14
End Date: 2025-08-15
Location: Intersection of Avenue D and Chestnut Street
Summary: Road reconstruction
Ave D between Chestnut and Mulberry, Chestnut Street between Ave D and Ave C. Lot 5 accessible via Sycamore. No sidewalk access along Ave D or Chestnut. Disrupted access for Chestnut and Chilton Halls.

 

Union Circle Realignment

Project Manager: City of Denton
Start Date: 2025-05-14
End Date: 2025-10-01
Location: Union Circle
Summary: Street reconstruction and realignment. Traffic flow on Union Circle will be reversed.
Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.

 

Replace Lot 20 Sanitary Sewer

Project Manager: Randy Salsman
Start Date: 2025-05-12
End Date: 2025-08-18
Location: Lot 20 Center Lane
Summary: Replace portion of sewer line infrastructure
Portion of the central access lane in Lot 20 will be closed and traffic redirected. Bus service to Lot 20 will be minimally impacted.

 

Hickory Street Landscaping Renovation

Project Manager: Brandon Lacy
Start Date: 2025-06-09
End Date: 2025-08-15
Location: Lawns and sidewalks north of Language, Auditorium, and Hickory Hall
Summary: Renovate landscaping
Sidewalk access will be blocked on the north side of Language, Auditorium, and Hickory Hall.

 

Highland Garage Landscaping Renovation

Project Manager: Brandon Lacy
Start Date: 2025-06-02
End Date: 2025-08-08
Location: Highland Street Parking Garage
Summary: Maintenance of trees and landscaping and updating irrigation
Sidewalk will be closed between Highland Street and the garage. Access to the garage and crosswalk will not be disrupted.

 

Chestnut Hall Landscaping Renovation

Project Manager: Brandon Lacy
Start Date: 2025-06-02
End Date: 2025-08-08
Location: South side of Chestnut Hall
Summary: Renovation of landscaping and irrigation south of Chestnut Hall
Pedestrian access to Chestnut Hall from the South may be disrupted.

 

Welch Street Construction

Project Manager: City of Denton
Start Date: 2025-07-07
End Date: 2025-10-01
Location: Welch Street between Mulberry and Sycamore
Summary: Utilities replacement and road reconstruction
No automobile traffic on Welch St between Mulberry and Sycamore. No pedestrian crosswalk.

June 2025 Report
Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-13

Project End Date: 2025-06-11

Location Description: Welch St between Highland St and Eagle Dr

Project Summary:  Road reconstruction

Areas Impacted: No automobile traffic on Welch St between Eagle and Highland. Westbound traffic may cross at Maple St. No sidewalk accessible across Maple St or Highland St.

 

Project Name: Mulberry St Construction

Project Manager: City of Denton

Project Start Date: 2024-12-03

Project End Date: 2025-07-03

Location Description: Mulberry Street

Project Summary:  Upgrading city water and sewer lines and street reconstruction.

Areas Impacted: Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.

 

Project Name: Prairie St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-25

Project End Date: 2025-09-25

Location Description: Prairie St between Bernard St and Welch St

Project Summary:  Replace water and sewer lines and street reconstruction

Areas Impacted: Automobile traffic will be disrupted. Lots 47 and 39 impacted.  Pedestrian and parking access to Welch Street Complex will be disrupted. No sidewalk access across Prairie St.

 

Project Name: Union Circle Realignment

Project Manager: City of Denton

Project Start Date: 2025-05-14

Project End Date: 2025-09-30

Location Description: Union Circle

Project Summary:  Street reconstruction and realignment. Traffic flow on Union Circle will be reversed.

Areas Impacted: Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.

 

Project Name: Avenue A Utilities

Project Manager: Tracy Beck & Scott Fettig - City of Denton

Project Start Date: 2025-02-21

Project End Date: 2025-06-26

Location Description: Avenue A between Eagle Dr and Maple St

Project Summary:  Replace water and sewer lines and street reconstruction

Areas Impacted: Project area open for traffic for resident move-out. Construction will resume May 12th. Closure of Avenue A between Maple and Eagle and Maple Street between Central and Avenue A. No pedestrian access.

 

Project Name: Ave D and Chestnut Street Construction

Project Manager: City of Denton

Project Start Date: 2025-05-14

Project End Date: 2025-08-31

Location Description: Intersection of Avenue D and Chestnut Street

Project Summary:  Street reconstruction

Areas Impacted: Ave D between Chestnut and Mulberry, Chestnut Street between Ave D and Ave C. Lot 5 accessible via Sycamore. No sidewalk access along Ave D or Chestnut. Disrupted access for Chestnut and Chilton Halls

 

Project Name: Bonnie Brae St Widening

Project Manager: City of Denton

Project Start Date: 2024-01-01

Project End Date: 2026-12-31

Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr

Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

 

Project Name: Replace Lot 20 Sanitary Sewer

Project Manager: Randy Salsman

Project Start Date: 2025-05-12

Project End Date: 2025-08-18

Location Description: Lot 20 Center Lane

Project Summary:  Replace portion of sewer line infrastructure

Areas Impacted: Portion of the central access lane in Lot 20 will be closed and traffic redirected. Bus service to Lot 20 will be minimally impacted.

 

Project Name: Hurley Courtyard Landscaping

Project Manager: Brandon Lacy

Project Start Date: 2025-05-19

Project End Date: 2025-07-11

Location Description: North side of Hurley Administration Building

Project Summary:  Renovations to the entry courtyard

Areas Impacted: Entrances to Hurley Administration will not be accessible for duration of project. Accessible entrance available on South side of building.

 

Project Name: Chilton Hall Sidewalk Expansion

Project Manager: Brandon Lacy

Project Start Date: 2025-05-12

Project End Date: 2025-07-31

Location Description: Chilton Hall East Side

Project Summary:  Landscaping upgrades and widening of sidewalk in front of Chilton Hall along Avenue C.

Areas Impacted: No sidewalk access along Avenue C. East entrance to Chilton Hall 2nd Floor will not be accessible.

 

Project Name: Chestnut Hall Landscaping Renovation

Project Manager: Brandon Lacy

Project Start Date: 2025-06-02

Project End Date: 2025-08-08

Location Description: South side of Chestnut Hall

Project Summary:  Renovation of landscaping and irrigation south of Chestnut Hall

Areas Impacted: Pedestrian access to Chestnut Hall from the South may be disrupted.

 

Project Name: Hickory Street Landscaping Renovation

Project Manager: Brandon Lacy

Project Start Date: 2025-06-09

Project End Date: 2025-08-15

Location Description: Lawns and sidewalks north of Language, Auditorium, and Hickory Hall

Project Summary:  Renovate landscaping

Areas Impacted: Sidewalk access will be blocked on the north side of Language, Auditorium, and Hickory Hall.

 

Project Name: Highland Garage Landscaping Renovation

Project Manager: Brandon Lacy

Project Start Date: 2025-06-02

Project End Date: 2025-08-08

Location Description: Highland Street Parking Garage

Project Summary:  Maintenance of trees and landscaping and updating irrigation

Areas Impacted: Sidewalk will be closed between Highland Street and the garage. Access to the garage and crosswalk will not be disrupted.

 

Project Name: Discovery Park Fire Piping Replacement

Project Manager: Carl Parsons, UNT

Project Start Date: 2025-02-03

Project End Date: 2026-08-04

Location Description: Discovery Park

Project Summary:  Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system

Areas Impacted: Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.

 

Project Name: Science and Tech. Building

Project Manager: Jay Henson, UNT System

Project Start Date: 2024-09-01

Project End Date: 2026-09-01

Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.

Project Summary:  Construction of new Science and Tech. building.

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

 

Project Name: Softball Clubhouse Construction

Project Manager: Jay Henson, UNT System

Project Start Date: 2025-02-03

Project End Date: 2025-12-31

Location Description: Mean Green Village Softball Field

Project Summary:  Improvement of dugouts and construction of new club house and offices.

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

 

Project Name: Intramual Fields Lighting and Irrigation Installation

Project Manager: Herman McKeiver, Yaggi Engineering

Project Start Date: 2024-08-01

Project End Date: 2025-09-01

Location Description: Intramural Fields at Bonnie Brae and Prairie

Project Summary:  Construction of new field lighting and irrigation systems for intramural fields

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.

May 2025 Report
Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-13

Project End Date: 2025-05-30

Location Description: Welch St between Highland St and Eagle Dr

Project Summary: Road reconstruction

Areas Impacted: No automobile traffic on Welch St between Eagle and Highland. Westbound traffic may cross at Maple St. No sidewalk accessible across Maple St or Highland St.

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-04-23

Project End Date: 2025-07-15

Location Description: Welch Street, between W Highland St and W Prairie St

Project Summary: Road reconstruction

Areas Impacted: Automobile and pedestrian traffic will be disrupted for the duration of the project. No crosswalk access at Welch and Prairie.

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-02-01

Project End Date: 2025-04-26

Location Description: Welch St between W Sycamore St and W Chestnut St/Union Circle

Project Summary: Road to be reconstructed

Areas Impacted: Automobile and pedestrian traffic will be disrupted for duration of the project. No crosswalk access at Chestnut or Sycamore St. Access to Lots 55 and 54 redirect via Bernard St.

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-04-23

Project End Date: 2025-07-14

Location Description: Welch St between W Sycamore St and W Mulberry St

Project Summary: Road reconstruction

Areas Impacted: Automobile and pedestrian traffic will be disrupted for duration of the project. No crosswalk access at Sycamore St. Access to Lots 55 and 54 redirect via Bernard St.

Project Name: Mulberry St Construction

Project Manager: City of Denton

Project Start Date: 2024-12-03

Project End Date: 2025-06-01

Location Description: Mulberry Street

Project Summary: Upgrading city water and sewer lines and street reconstruction.

Areas Impacted: Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.

Project Name: Prairie St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-25

Project End Date: 2025-09-25

Location Description: Prairie St between Bernard St and Welch St

Project Summary: Replace water and sewer lines and street reconstruction

Areas Impacted: Automobile traffic will be disrupted. Lots 47 and 39 impacted.  Pedestrian and parking access to Welch Street Complex will be disrupted. No sidewalk access across Prairie St.

Project Name: Union Circle Realignment

Project Manager: City of Denton

Project Start Date: 2025-05-14

Project End Date: 2025-09-30

Location Description: Union Circle

Project Summary: Street reconstruction and realignment. Traffic flow on Union Circle will be reversed.

Areas Impacted: Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.

Project Name: Avenue A Utilities

Project Manager: Tracy Beck & Scott Fettig - City of Denton

Project Start Date: 2025-02-21

Project End Date: 2025-06-26

Location Description: Avenue A between Eagle Dr and Maple St

Project Summary: Replace water and sewer lines and street reconstruction

Areas Impacted: Automobile traffic will be disrupted. Intersection closed at Maple Street. No pedestrian access across Avenue A at Maple Street. Access to lots 33 and 32 will be impacted.

Project Name: Ave D and Chestnut Street Construction

Project Manager: City of Denton

Project Start Date: 2025-05-14

Project End Date: 2025-08-31

Location Description: Intersection of Avenue D and Chestnut Street

Project Summary: Street reconstruction

Areas Impacted: Avenue D between Chestnut Street and West Sycamore Street and Chestnut Street between Avenue D and Avenue C. Will impact access to Physical Education, Pohl Rec Center, Chestnut, Chilton, Lot 5 and 4.

Project Name: Bonnie Brae St Widening

Project Manager: City of Denton

Project Start Date: 2024-01-01

Project End Date: 2026-12-31

Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr

Project Summary: Installation of underground utilities and roadway expansion to four-lane divided highway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Project Name: Science and Tech. Building

Project Manager: Jay Henson, UNT System

Project Start Date: 2024-09-01

Project End Date: 2026-09-01

Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.

Project Summary: Construction of new Science and Tech. building.

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Name: Performing Arts Center Electrical

Project Manager: Carl Parsons

Project Start Date: 2025-04-18

Project End Date: 2025-05-05

Location Description: Eagle Drive at I-35 and North side of Murchison Performing Arts Center

Project Summary: Installation of subsurface electrical lines.

Areas Impacted: Pedestrian access to Murchison Performing Arts Center and Annex will be disrupted while trench is open. Parking at Performing Arts Annex will be disrupted throughout the project. Lot 20 will be open.

Project Name: Discovery Park Fire Piping Replacement

Project Manager: Carl Parsons, UNT

Project Start Date: 2025-02-03

Project End Date: 2026-08-04

Location Description: Discovery Park

Project Summary: Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system

Areas Impacted: Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.

Project Name: Intramual Fields Lighting and Irrigation Installation

Project Manager: Herman McKeiver, Yaggi Engineering

Project Start Date: 2024-08-01

Project End Date: 2025-09-01

Location Description: Intramural Fields at Bonnie Brae and Prairie

Project Summary: Construction of new field lighting and irrigation systems for intramural fields

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.

Project Name: Softball Clubhouse Construction

Project Manager: Jay Henson, UNT System

Project Start Date: 2025-02-03

Project End Date: 2025-12-31

Location Description: Mean Green Village Softball Field

Project Summary: Improvement of dugouts and construction of new club house and offices.

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

Project Name: Lot 20 Sewer Work

Project Manager: Vince Stippec

Project Start Date: 2025-05-12

Project End Date: 2025-07-01

Location Description: Lot 20 Center Lane

Project Summary: Replacement of sewer line

Areas Impacted: Portion of the central access lane in Lot 20 will be closed and traffic redirected. Bus service to Lot 20 will be minimally impacted.

Project Name: Chilton Hall Sidewalk Expansion

Project Manager: Brandon Lacy

Project Start Date: 2025-05-12

Project End Date: 2025-07-31

Location Description: Chilton Hall East Side

Project Summary: Landscaping upgrades and widening of sidewalk in front of Chilton Hall along Avenue C.

Areas Impacted: No sidewalk access along Avenue C. East entrance to Chilton Hall 2nd Floor will not be accessible.

Project Name: Gateway Class Ring Sculpture

Project Manager: Brandon Lacy

Project Start Date: 2025-05-05

Project End Date: 2025-05-30

Location Description: Gateway Center

Project Summary: Installation of UNT Class Ring sculpture and base with lighting and drainage

Areas Impacted: Sidewalk beneath the arch of Gateway Center will be partially blocked, building entrances will remain accessible.


April 2025 Report
Project Name: Welch St Construction
Project Manager: City of Denton
Project Start Date: 2025-03-13
Project End Date: 2025-05-30
Location Description: Welch St between Highland St and Eagle Dr
Project Summary:  Road reconstruction
Areas Impacted: No automobile traffic on Welch St between Eagle and Highland. Westbound traffic may cross at Maple St. No sidewalk accessible across Maple St or Highland St.
 
Project Name: Welch St Construction
Project Manager: City of Denton
Project Start Date: 2025-02-01
Project End Date: 2025-04-26
Location Description: Welch St between W Mulberry St and W Chestnut St/Union Circle
Project Summary:  Road reconstruction
Areas Impacted: Welch St closed between Chestnut St and Sycamore St until the portion of Welch St between W Mulberry and W Hickory is completed. Traffic to Lot 50 redirected through Union Circle.
 
Project Name: Welch St Construction
Project Manager: City of Denton
Project Start Date: 2025-01-06
Project End Date: 2025-04-02
Location Description: Welch Street, between W Prairie St and Chestnut St
Project Summary:  Road reconstruction
Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project. Access to Lot 47 will be blocked.
Project Name: Mulberry St Construction
Project Manager: City of Denton
Project Start Date: 2024-12-03
Project End Date: 2025-06-01
Location Description: Mulberry Street
Project Summary:  Upgrading city water and sewer lines and street reconstruction
Areas Impacted: Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.
 
Project Name: Prairie St Construction
Project Manager: City of Denton
Project Start Date: 2025-03-25
Project End Date: 2025-05-12
Location Description: Prairie St between Bernard St and Welch St
Project Summary:  Upgrading city water and sewer lines and street reconstruction
Areas Impacted: Automobile traffic will be disrupted. Lots 47 and 39 impacted.  Pedestrian and parking access to Welch Street Complex will be disrupted. No sidewalk access across Prairie St.
 
Project Name: Bonnie Brae St Widening
Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway
Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.
 
Project Name: Science and Tech. Building
Project Manager: Jay Henson, UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street
Project Summary:  Construction of new Science and Tech. building
Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.
 
Project Name: Performing Arts Center Electrical
Project Manager: Carl Parsons
Project Start Date: 2025-04-18
Project End Date: 2025-05-05
Location Description: Eagle Drive at I-35 and North side of Murchison Performing Arts Center
Project Summary:  Installation of subsurface electrical lines
Areas Impacted: Pedestrian access to Murchison Performing Arts Center and Annex will be disrupted while trench is open. Parking at Performing Arts Annex will be disrupted throughout the project. Lot 20 will be open.
 
Project Name: Discovery Park Fire Piping Replacement
Project Manager: Carl Parsons, UNT
Project Start Date: 2025-02-03
Project End Date: 2026-08-04
Location Description: Discovery Park
Project Summary:  Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system
Areas Impacted: Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.
 
Project Name: Intramural Fields Lighting and Irrigation Installation
Project Manager: Herman McKeiver
Project Start Date: 2024-08-01
Project End Date: 2025-09-01
Location Description: Intramural Fields at Bonnie Brae and Prairie
Project Summary:  Construction of new field lighting and irrigation systems for intramural fields
Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.
 
Project Name: Softball Clubhouse Construction
Project Manager: Jay Henson, UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary:  Improvement of dugouts and construction of new club house and offices.
Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.
February 2025 Report
Project Name: Welch St Utilities

Project Manager: City of Denton

Project Start Date: 2024-11-20

Project End Date: 2025-02-19

Location Description: Welch St between W Hickory St and W Mulberry St

Project Summary: Replacement of water and sewer lines.

Areas Impacted: Through traffic is blocked. Intersections to remain open.

 

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-02-01

Project End Date: 2025-04-26

Location Description: Welch St between W Mulberry St and W Chestnut St/Union Circle

Project Summary: Road to be reconstructed

Areas Impacted: Through traffic will be blocked. Intersection with W Sycamore St will be blocked. Access to Lot 50 may be impacted.

 

Project Name: Intramual Fields Lighting and Irrigation Installation

Project Manager: Herman McKeiver, Yaggi Engineering

Project Start Date: 2024-08-01

Project End Date: 2025-09-01

Location Description: Intramural Fields at Bonnie Brae and Prairie

Project Summary: Construction of new field lighting and irrigation systems for intramural fields

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street

 

Project Name: Mulberry St Construction

Project Manager: City of Denton

Project Start Date: 2024-12-03

Project End Date: 2025-06-02

Location Description: Mulberry Street

Project Summary: Upgrading city water and sewer lines and street reconstruction.

Areas Impacted: Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.

 

Project Name: Discovery Park Fire Piping Replacement

Project Manager: Carl Parsons, UNT

Project Start Date: 2025-02-03

Project End Date: 2026-08-04

Location Description: Discovery Park

Project Summary: Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system

Areas Impacted: Discovery Park and parking lots

 

Project Name: Bonnie Brae St Widening

Project Manager: City of Denton

Project Start Date: 2024-01-01

Project End Date: 2026-12-31

Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr

Project Summary: Installation of underground utilities and roadway expansion to four-lane divided highway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

 

Project Name: Science and Tech. Building

Project Manager: Hannah Aikin

Project Start Date: 2024-09-01

Project End Date: 2026-09-01

Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.

Project Summary: Construction of new Science and Tech. building.

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

 

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-01-06

Project End Date: 2025-04-02

Location Description: Welch Street, between W Prairie St and Chestnut St

Project Summary: Road reconstruction

Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project

 

Project Name: Avenue A Utilities

Project Manager: Tracy Beck & Scott Fettig - City of Denton

Project Start Date: 2025-02-21

Project End Date: 2025-06-26

Location Description: Avenue A between Eagle Dr and Maple St

Project Summary: Replace water and sewer lines and street reconstruction

Areas Impacted: Automobile traffic will be disrupted. Intersecting streets to remain open. Access to Lots 33 and 32 will be impacted.

 

Project Name: Softball Clubhouse Construction

Project Manager: Jay Henson, UNT System

Project Start Date: 2025-02-03

Project End Date: 2025-12-31

Location Description: Mean Green Village Softball Field

Project Summary: Improvement of dugouts and construction of new club house and offices.

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

August 2024 Report

Project Name: Auditorium Subgrade

Project Manager: Kerri Nidenberg

Project Start Date: 07/07/2024

Project End Date: 12/20/2024

Location Description: Auditorium building, entrances and sidewalks on the north side facing Hickory Street.

Project Summary: Applying a waterproof membrane to prevent foundation problems down the road.

Areas Impacted: Pedestrian traffic will be intermittently disrupted for the duration of the project

 

Project Name: Bonnie Brae Widening Phase 3

Project Manager: City of Denton

Project Start Date: 01/01/2024

Project End Date: 12/31/2026

Location Description: Roselawn Avenue.

Project Summary: Installation of underground utilities and roadway expansion to four-lane divided highway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

 

Project Name: Welch St Water Line Installation

Project Manager: City of Denton

Project Start Date: 06/03/2024

Location Description: Welch Street, between W Chestnut Street and W Prairie Street.

Project Summary: Replacement of underground water line.

Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project.

 

Project Name: Ave C Reconstruction

Project Manager: City of Denton

Project Start Date: August 12, 2024

Project End Date: January 31, 2025

Location Description: Avenue C, between W Highland Street and Eagle Drive.

Project Summary: Reconstruction of road and surrounding sidewalks.

Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project.

 

Project Name: Science and Tech. Building

Project Manager: Hannah Aikin

Project Start Date: 09/01/2024

Project End Date: 09/01/2026

Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.

Project Summary: Construction of new Science and Tech. building.

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

 

June 2024 Report

Project Name: Avenue D Utility Installation

Project Manager: City of Denton

Project Start Date: 2024-06-03

Project End Date: 2024-08-12

Location Description: Avenue D, between W Mulberry Street and W Chestnut Street.

Project Summary: Replacement of underground utilities.

Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project.

 

Project Name: Chestnut Street Utility Installation

Project Manager: City of Denton

Project Start Date: 2024-06-03

Project End Date: 2024-08-12

Location Description: W Chestnut Street, between Avenue D and Avenue C.

Project Summary: Replacement of underground utilities.

Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project.

 

Project Name: Welch St Water Line Installation

Project Manager: City of Denton

Project Start Date: 2024-06-03

Project End Date: 2024-08-12

Location Description: Welch Street, between W Highland Street and Eagle Drive.

Project Summary: Replacement of underground water line.

Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project.

 

Project Name: Central Avenue Utility Installation

Project Manager: City of Denton

Project Start Date: 2024-06-04

Project End Date: 2024-08-12

Location Description: Central Avenue, between W Highland St and Maple St.

Project Summary: Replacement of underground utilities.

Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project.

 

Project Name: Maple Street Road Repair

Project Manager: City of Denton

Project Start Date: 2024-01-22

Project End Date: 2024-08-01

Location Description: Maple St from Avenue D to Avenue A.

Project Summary: Reconstruction of roadway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Additional Information: Find the Maple Street Page here.

 

Project Name: Bonnie Brae Utility Installation

Project Manager: City of Denton

Project Start Date: 2024-01-01

Project End Date: 2026-12-31

Location Description: Bonnie Brae Street, from Airport Rd to Willowwood St.

Project Summary: Installation of underground utilities and roadway expansion to four-lane divided highway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.