Construction Obstruction Report

This page contains links and information to Facilities’ monthly construction reports, which detail where you can expect to find campus mobility obstructed by construction activities.

 

October 2023 Construction Obstruction Report

 

Project Name: Coliseum Fire Systems Utilities Update

Project Manager: Scott Harris

Project Start Date: 2023-07-31

Project End Date: 2023-12-31

Location Description: Area between Coliseum and Gateway Center, continuing to the south corner of Ave D and Maple Street

Project Summary: Update of the fire suppression systems utility line

Areas Impacted: Pedestrian traffic will be disrupted for the duration of the project

 

 

Project Name: Avenue C Gas Main Replacement

Project Manager: Superior Pipeline Services

Project Start Date: 2023-09-18

Project End Date: 2023-11-03

Location Description: Avenue C between W Highland St and Maple St

Project Summary: Replacement of underground gas main

Areas Impacted: Pedestrian and vehicular traffic will be disrupted for the duration of the project

 

 

Project Name: UNT Advanced Air Mobility Test Center Installation

Project Manager: Kim Nguyen

Project Start Date: 2023-09-25

Project End Date: 2023-11-10

Location Description: Grass area north of UNT Discovery Park

Project Summary: Construction of the UNT Advanced Air Mobility Test Center

Areas Impacted: Pedestrian traffic will be disrupted for the duration of the project

 

 

Project Name: Irrigation Utility Installation

Project Manager: Sam Chambliss

Project Start Date: 2023-09-20

Project End Date: 2023-10-06

Location Description: Sidewalk to the northeast of the University Union Building

Project Summary: Installation of underground irrigation lines

Areas Impacted: Pedestrian traffic will be disrupted for the duration of the project