Construction Report

This page contains links and information to Facilities’ monthly construction reports, which detail where you can expect to find campus mobility obstructed by construction activities.

Click on the construction areas in the map to find more information, or open the map in a new window by clicking here. The attachment at the bottom of the page is a link to a text-only report of this information.

 

August 2019 Construction Obstruction Report

 

Project Name: Central Dining Hall

Project Lead: Jeannine Vail

Project Start Date: 2/11/2019

Project End Date: 6/30/2020

Location Description: Greenspace east of Business Leadership Building

Project Summary: Build new dining facility

Areas Impacted: Pedestrian traffic will be blocked for duration of project.

 

Project Name: Coliseum Roof Repair

Project Lead: Gilly Gilland

Project Start Date: 2/25/2019

Project End Date: 12/31/2019

Location Description: Coliseum Roof

Project Summary: Repair roof and replace metal panels.

Areas Impacted: SW corner of building blocked to pedestrians.

 

Project Name: College Inn Stairwell

Project Lead: Jeff Hilliard

Project Start Date: 5/20/2019

Project End Date: 8/2/2019

Location Description: Lot 12 area

Project Summary: Construct new egress stairway.

Areas Impacted: Vehicular and pedestrian traffic will be blocked for project duration.

 

Project Name: Facilities Fuel Tank Replacement

Project Lead: Chad Davenport

Project Start Date: 5/1/2019

Project End Date: 8/31/2019

Location Description: Southeast corner of Automotive Services

Project Summary: Replace current fuel tanks and upgrade to current Federal standards

Areas Impacted: Vehicular and pedestrian traffic will be blocked during construction.

 

Project Name: Hickory Street Capital Improvement

Project Lead: City of Denton

Project Start Date: 6/4/2019

Project End Date: 8/16/2019

Location Description: Hickory Street between Avenue B and Welch Street

Project Summary: Reconstruct the road base

Areas Impacted: Pedestrian traffic and vehicular traffic will be blocked as needed for the duration of the project.

 

Project Name: Hurley Administration Landscaping PH II

Project Lead: Chad Davenport

Project Start Date: 5/26/2019

Project End Date: 8/31/2019

Location Description: South of Hurley Admin Building

Project Summary: Improve walkway and landscaping.

Areas Impacted: Pedestrian traffic will be blocked for the duration of project.

 

Project Name: Indoor Practice Facility

Project Lead: Terri Pierce

Project Start Date: 9/12/2018

Project End Date: 9/30/2019

Location Description: Football practice fields

Project Summary: Build new indoor practice facility.

Areas Impacted: Pedestrian traffic will be blocked for project duration.

 

Project Name: Life Science Exhaust Upgrade

Project Lead: Scott Harris

Project Start Date: 5/11/2019

Project End Date: 8/25/2019

Location Description: Lot 8 parking lot

Project Summary: Upgrade lab fume hoods

Areas Impacted: Parking lot will be closed to traffic for the duration of the project.

 

Project Name: Lot 20 Expansion

Project Lead: Traci Jones

Project Start Date: 1/2/2019

Project End Date: 8/31/2019

Location Description: Lot 20 from North Texas Boulevard to the USB Building

Project Summary: Demolish Fouts Field and reconstruct parking lot.

Areas Impacted: No vehicular or pedestrian traffic within the confines of the construction site.

 

Project Name: Music Courtyard Renovation

Project Lead: Janell Cottam

Project Start Date: 5/15/2019

Project End Date: 9/30/2019

Location Description: Music Building courtyard

Project Summary: Renovate courtyard area outside Voertman Hall lobby

Areas Impacted: Pedestrian traffic will be blocked during construction.

 

Project Name: SRB Greenhouse

Project Lead: Chad Davenport

Project Start Date: 4/1/2019

Project End Date: 9/30/2019

Location Description: SW corner of Science Research Building

Project Summary: Build new greenhouse

Areas Impacted: Pedestrians and parking will be restricted for duration

 

Project Name: Starbucks Stand Construction

Project Lead: Brandon Lacy

Project Start Date: 6/1/2019

Project End Date: 9/8/2019

Location Description: South of Lot 1

Project Summary: Build new retail space and improve landscaping and paving.

Areas Impacted: Pedestrian traffic will be blocked for duration of project.

 

Project Name: Willis Library Waterproofing

Project Lead: Randy Salsman

Project Start Date: 1/19/2019

Project End Date: 7/31/2019

Location Description: West and south side of library building

Project Summary: Waterproof foundation

Areas Impacted: Pedestrian traffic may be impacted along south side of building