Construction Report

This page contains links and information to Facilities’ monthly construction reports, which detail where you can expect to find campus mobility obstructed by construction activities.

Click on the construction areas in the map to find more information, or open the map in a new window by clicking here. The attachment at the bottom of the page is a link to a text-only report of this information.

October 2019 Construction Obstruction Report

 

Project Name: Indoor Practice Facility

Project Lead: Terri Pierce

Project Start Date: 9/12/2018

Project End Date: 10/31/2019

Location Description: Football practice fields

Project Summary: Build new indoor practice facility.

Areas Impacted: Pedestrian traffic will be blocked for project duration.

 

Project Name: Central Dining Hall

Project Lead: Jeannine Vail

Project Start Date: 2/11/2019

Project End Date: 6/30/2020

Location Description: Greenspace east of Business Leadership Building

Project Summary: Build new dining facility

Areas Impacted: Pedestrian traffic will be blocked for duration of project.

 

Project Name: SRB Greenhouse

Project Lead: Chad Davenport

Project Start Date: 4/1/2019

Project End Date: 10/12/2019

Location Description: SW corner of Science Research Building

Project Summary: Build new greenhouse

Areas Impacted: Pedestrians and parking will be restricted for duration

 

Project Name: Hickory Street Capital Improvement

Project Lead: City of Denton

Project Start Date: 8/12/2019

Project End Date: 12/19/2019

Location Description: Hickory Street between Avenue B and Welch Street

Project Summary: Reconstruct the road base

Areas Impacted: Pedestrian traffic and vehicular traffic will be blocked as needed for the duration of the project.

 

Project Name: Music Courtyard Renovation

Project Lead: Janell Cottam

Project Start Date: 5/15/2019

Project End Date: 10/19/2019

Location Description: Music Building courtyard

Project Summary: Renovate courtyard area outside Voertman Hall lobby

Areas Impacted: Pedestrian traffic will be blocked during construction.

 

Project Name: Coliseum Roof Repair

Project Lead: Gilly Gilland

Project Start Date: 2/25/2019

Project End Date: 12/31/2019

Location Description: Coliseum Roof

Project Summary: Repair roof and replace metal panels.

Areas Impacted: SW corner of building blocked to pedestrians.

 

Project Name: Facilities Fuel Tank Replacement

Project Lead: Chad Davenport

Project Start Date: 5/1/2019

Project End Date: 10/12/2019

Location Description: Southeast corner of Automotive Services

Project Summary: Replace current fuel tanks and upgrade to current Federal standards

Areas Impacted: Vehicular and pedestrian traffic will be blocked during construction.